Emergency Cross Pipe Replacement

The Township thanks Representative John Hornaman for supporting our request for emergency funding from the state to help with the extraordinary cost for this replacement.  We expect to receive Community Revitalization Program funds of $10,000, which will help us recover from the elimination of services necessitated to fund the replacement of the cross pipe.

On July 23-24 about three inches of rain fell in 6 hours which caused the failure of a large cross pipe on Francis Road between Brooks and Mohawk Roads. 

 

Because this is a vital transportation route, it's actually the second most traveled road in Franklin Township, the Supervisors elected to replace the pipe on an emergency basis. 

 

Permits were secured and vendors were contacted and bid the work.

 

Chivers Construction was the low bidder.  The Township purchased the pipe from Lane Metal for nearly $27,000.  After engineering, installation and materials purchases the anticipated replacement cost is nearly $80,000. 

 

Because this is a substantial amount and funds were not available, the Supervisors decided to eliminate the gravel program and discontinue other maintenance programs planned to be completed during the remainder of the year.  Instead the Township crew will only do minimum maintenance and will shorten their work schedule. 

 

Through these measures the Township will have enough funds to do the replacement. 

 

Below find pictures of the replacement.

 

Francis Road reopened at 6 pm on September 3, 2008


July 24:
Large hole appeared  after rainstorm indicating washout and undermining of pipe


Day 1:
Old pipe after removal


Day 1:
Excess material is piled on road and will be reused


Day 1:
New 7' diameter pipe will be set slightly below creek level.


Day 1:
Finishing the  excavation  and preparing for bedding stone


Day 1:
John Hess Chivers foreman on the job.


Day 2:
Pipe assembly of 7 foot diameter structural plate round pipe--2445 bolts and nuts


Day 2:
About half of the 130 foot pipe is assembled

Day 2: George Pushkar, inspecting the installation on behalf of the Township's Engineer Mark Cory


Day 3:
Pipe assembly continues


Day 4:
Last pieces of pipe being set and bolted together


Day 4:
View toward inlet end


Day 4:
View of outlet end


Day: 4
Stockpiled original material is reused for cover.  View west Francis Rd


Day 4:
View east on Francis Rd
Labor Day Weekend:
Excavator holding pipe down, just in case, while crew takes several days of rest

Day 5:
Large R-7 rock brought in to protect the inlet and roadside berm from erosion

Day 5:
Erosion protect rock being placed along road berm and in front of inlet

Day 6:

Site clean up in progress

Day 6:

Finished inlet


Day 6:

Old pipe being smashed to be hauled to the scrap yard


Day 6:

Finished outlet
Francis Road Reopened at 6 pm, Sept 3, 2008  

 Copyright © 2011 Franklin Township. All rights reserved.
Revised: 02/02/11.