|
Cross pipe replacement began July
1 and was completed July 19th.
At each cross pipe location the old pipe is
removed. As you can see the steel pipe has disintegrated from rust
due to age. The ditch for the pipe is dug to a predetermined grade.
All creatures and objects large and small are found in our pipe trenches. This
is 3-foot garter snake. The basketball ball was found stuck in the
middle of one cross pipe. Large cement blocks 2' x 2' x 6' are used to
provide end walls to limit erosion. The ditch is prepared by placing
about 3 inches of #57 stone bedding. The pipes are placed in the
ditch and backfilled at least half way with stone. Then the
remaining ditch is filled with gravel, compacted and smoothed over with
the backhoe. The old pipe is trucked back to the Township Building
for later recycling. Most pipe locations are getting two new plastic
cross pipes. One waterway required five pipes side-by-side. |

 |
|
Pictures taken
July 1-16, 2002 |
|
|
|
In the 'old days' when the spring
roads were soft...
The farmers and residents often encountered soft,
springtime road conditions. Their solution was to place tree trunks,
slab wood or railroad ties along with rocks picked from their fields into
the soft, impassable areas. Here are two tree trunks and rocks
being excavated as we are cutting a trench to install a new cross pipe. |
|
 |
|
Pictures taken
July 15, 2002 |
|
|
|
On Rain days we're working on
ditching and driveways
A jet truck from National Vacuum was used to
clear mud from two 40-foot well casings used as gas well driveway pipes.
The truck pumps high pressure water into a hose with a special nozzle.
The high pressure water stream blasts the debris from the pipe.
James Ireland and Dave Kelly show the nozzle. |
|
 |
|
Pictures
taken July 9, 2002 |
|
|
|
Under drain installation was
completed June 28
Under
drain locations were selected based on past soft, spring-time road
conditions. At each location a diagonal trench is cut through a soft
area. Loose material is removed from the trench. AdvanEdge
drain is installed. This drain tile is about 12" high and 1.5 inches
wide, is wrapped with filter fabric and fits neatly in the trench.
The trench is then backfilled with crushed limestone to slightly below the
original road level. A backhoe is used to cover over and smooth the
surface. This project is using a trencher from PennDOT under the
Agility Program. Our PennDOT Agility operator is Robert "Bucky"
Buckwalter. |
|

    |
|
Pictures taken
June 26, 2002 |
|
|
|
Preparatory work.
Monday, Aug 12, we received the geotextile fabric
and unloaded it at three stockpile locations. |
|
 |
|
|
|
Also on Monday we removed material on the approach
to Crane Road to allow for a full-depth of subbase to be installed.
We were in the process of removing material at New and Eureka Roads when
we got rained out. While the Township crew was doing this, Russell
Standard was grading the road to the proper profile. |
|
 |
|
Pictures taken
August 12, 2002 |