|





















| |
Eureka Road Paving Project Photos--Page
2
2004 Activities
Click here to see our
2002 activities--Page 1.
|
Geotextile and Subbase
Gravel
Tuesday, Aug. 13, 2002 work began on the installation
of the geotextile fabric and the subbase gravel. First the
road is scarified to provide a rough, non-slip surface. Then the
geotextile fabric is laid. Fifteen trucks were lined up ready to dump. The trucks
dump gravel into a Roadtec "Shuttle Buggy" that provides additional mixing and
transports the gravel into the paving machine. Following the paving
machine is a steel-wheeled vibratory roller to compact the gravel to
maximum density. Two layers of gravel was installed to create a
subbase of 8 inches. The subbase installation was completed Aug. 16. |
|

 |
|
Pictures taken
August 13, 2002 |
Copyright © 2010 Franklin Township.
All rights reserved.
Revised: 01/04/10.
|