June 6--Parapet walls are poured today
|
|
|
|
June 6--Concrete is thoroughly vibrated to remove any air pockets and insure uniformity of the concrete.
|
|
|
|
June 6--Top of the wall is smoothed and finished by hand.
|
|
|
|
|
June 15--Subbase is being prepared for asphalt placement.
|
|
|
|
June 20--Paving is completed today
|
|
|
|
June 20--Asphalt is placed over a newly installed 6" subbase of gravel
|
|
|
|
|
June 20--Asphalt is placed in one lane and then the other
|
|
|
|
June 20--4 1/2" base course to be followed by a 1 1/2" wearing course.
|
|
|
|
June 21--Guiderail installed today by Penn Line Service
|
|
|
|
|
Ken Huff (L), project foreman talks with Dennis Morian, Director of Engineering for Quality Engineering Solutions
|
|
|
|
Superintendent Rankin Montgomery of Quality Engineering Solutions, operates excavator
|
|
|
|
Ken Williams, Engineering Inspector, representing Mark Corey, P.E. and Associates, the Township's Engineer and bridge designer
|
|
|